A construction company needs to remove 18 tons of dirt from a construction site. They can remove 2/3 tons of dirt each hour. How long will take to remove the dirt? Write your answer in simplest form

Respuesta :

wegnerkolmp2741o
wegnerkolmp2741o wegnerkolmp2741o
  • 21-07-2021

Answer:

27 hours

Step-by-step explanation:

Take the amount of dirt and divide by the amount per hour

18 tons ÷ 2/3 ton per hour

Copy dot flip

18 * 3/2

Rewriting

18/2 * 3/1

9*3 = 27

27 hours

Answer Link

Otras preguntas

How does conservatism help to reduce air pollution
f(x)=x^2+x-30 complete the square
Find the range of y = 3cos4x - 2. -5 ≤ y ≤ 5 -5 ≤ y ≤ 1 -3 ≤ y ≤ 3 1 ≤ y ≤ 3
Pagamos el dinero. Compramos la comida para el cumplea?os. Fuimos a casa. Fuimos de compras a la Vega Central.
1) The sum of the lengths of two opposite sides of the circumscribed quadrilateral is 12 cm, the length of a radius of the circle is 2 cm. Find the area of the
What is the full name of the F-Scale and who came up with it?
could someone help me plzz :) solve and graph each inequality.​
What percentage of all living things that have ever existed on Earth are now extinct? a. 50 percent b. 70 percent c. 85 percent d. 99 pe
15 points What is the frequency of expression of dominant traits What is the frequency of expression of recessive traits
what is some entertainment in Nigeria? i will mark brainliest