1.Given the following information, sketch out the network diagram.

2. Identify the different network paths through the project.

3. What is the critical path? How many days is the critical path?

Task Duration Predecessor
A 3
B 5 A
C 12 A
D 9 B
E 14 C
F 3 B
G 4 D
H 7 F, G
I 2 E, H

Respuesta :

Otras preguntas

Convert 3/11 into a percent?
Convert 3/11 into a percent?
What military strategy defeated Cornwallis at Yorktown?
please solve the following equation. x-6x=56
what is the phenotype of a heterozygous person using T for tall and t for short
Dennis had a piece of rope that was 2.7 m long. He cut the rope into 3 equal pieces. Was each piece of rope greater than or less than 1 m?
How do you use implicit differentiation to find x^2+3xy+y^3=10
which process breaks down sugars to make atp when oxygen is present
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
How do you use implicit differentiation to find x^2+3xy+y^3=10