Following details regarding cost estimate of a project is given:

Optimistic cost = $ 8,000
Most likely cost = $ 10,000
Pessimistic cost = $ 15,000

Calculate the three-point estimate using triangular distribution.

a) $5,500
b) $10,500
c) $50,500
d) $11,000

Respuesta :

Otras preguntas

thomas has a square swimming pool at home. Each side is 18 m long. What is the area of the swimming pool
Which of Lincoln’s speeches is best reflected in this political cartoon?
-6•f (-3) - 5•g (-7) = please help.
A jar contains 22 blue, 10 navy, 22 pink, and 12 orange marbles. A marble is drawn at random. What is the probability that the marble is blue? (Answers are roun
Brainliest for anyone if they get this CORRECT.
Select the value of the 8 in the following number. 409.58
¿Por que el señor luna "trabajaba" como asesino?
"Just look at the graph," the player's agent said. "Phil's hits have doubled since last year. We are looking for a large raiseand a long contract."Look at the g
80 as the product of its prime factors
Find the distance between the points (2, 3) and (2,8).​