If the flow time for a process decreases, then the time to finish X units starting with empty inventory buffers will ______.

Respuesta :

palazzolorachel palazzolorachel
  • 18-02-2022
a. decrease
(
Time to finish X units starting with an empty system = Time through an empty process + [(X - 1) x Cycle time]
)
3.5
Answer Link

Otras preguntas

The gas in a cylinder has a volume of 3 liters at a pressure of 100 kPa. The pressure of the gas is increased to 203 kPa. Assuming the temperature remains const
Why was the establishment of CNN in 1980 so important? a. Because it provided news around the clock B. Because it used the first news flash C. Because it was th
president Roosevelts new deal created programs that werea. administered by the federal governmentb. based on the principles of the great societyc. considered co
HELPP At a grocery store, the price of milk decreased from $2.98 to $2.32. What is the percent of decrease, rounded to the nearest whole numbe
A ramp is an example of an inclined plane. A man in a wheelchair was trying to get up the ramp, but he was having trouble because it was too steep. What can you
Which techniques are used to engage a reader?
please help me!? Explain why i got this wrong ? how to do it right?
What do you need to know for the Music Theory Finals?
Does anyone know -6/7+6/21
if I am 300 years old reduced by 3 times my age is 39